Project Profiles : FDOT
FDOT Project Profile

FDOT

Community Asphalt

Project 1 - Community Asphalt

We have teamed with Community Asphalt on several DOT projects throughout the years. This featured project required approximately 4000 yards of Flow able Fill to repair water erosion and set new pipe.

Although this was not a large pour it required challenges in timely placement. We produced 460 yards per hour and placed concrete by feeding through two pumps and straight out of the trucks.

PCL Civil Constructors

Project 2 - PCL Civil Constructors

Concrete Paving - Interstate 95 Weigh in Motion Station Hobe Sound Florida
The state of the art facility is the first of its kind in the area. The project has over 16,000 yards of concrete paving and construction. It has required 200 yards per hour of concrete production. Having a massive subterranean scale, on and off ramps, an inspection building, and weigh in motion sensing scales.

Archer Western Contractors

Project 3 - Archer Western Contractors - The Walsh Group

I-95 Add Lanes and Reconstruction Project
Through Archer Western and their sub contractors we supplied over 19,000 cu. Yards of DOT concrete.

The project pours included barrier walls, auger cast piles, slip form, bridge deck and mass concrete foundations. We met the challenge of Archer Westerns tough schedule demand to help them complete this project ahead of schedule.

FDOT Projects

> Community Asphalt

> PCL Civil

> Archer Western


Copyright © 2009
Maschmeyer Concrete Company of Florida.
All rights reserved.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
Administrative Offices:
1142 Watertower Road, Lake Park, FL 33403
Phone: 561-844-9994 // Fax: 561-844-7102
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.